1. Check if all parts are flawless and sturdy, the power supply voltage is normal, and the air circuit is normal.


2. Check whether the sensors of socket chain, cup holder, cam, switch and color code are flawless and reliable.


3. Check whether the connection and smoothness of all mechanical parts are good.


4. Check whether the top tube station, pressure tube station, dimming station, filling station and sealing station are coordinated.


5. Clear things and other items aroQund the equipment.


6. Check whether all parts of the feeder set are free and solid.


7. Check that the control switch is in the original position and use the manual wheel machine to determine if there is any problem.


8. After confirming that the previous process is normal, turn on the power and air valve, and push the machine lightly for trial operation, first at low speed, and gradually increase to normal operation speed after normal.


9. Adjust the speed of the upper tube motor at the upper tube station so that the speed of its electric drawbar matches the speed of the machine, and keep the active tube dropping operation.


10. Pressing station drives the pressure head to operate simultaneously through the up and down reciprocating motion of cam linkage mechanism to press the hose to the correct position.

內(nèi)加熱灌裝封尾機


11. to the lighting position, arrive at the lighting alignment station with a trolley, rotate the lighting alignment cam so that it operates towards the lighting cam proximity switch and make the light beam of the photoelectric switch shine at 5 - 10 mm intervals from the center of the color code.


12. Filling station is that when the hose is lifted at the lighting station, the probe tube near switch at the top of the top tube cone end will be turned on by the PLC signal and then operated by the solenoid valve, and the filling and discharging of the paste will be finished when the end of the hose is detached by 20 mm.


13. Adjust the filling amount by loosening the nut first, then add it outward when tightening the corresponding screw and moving the slider of the travel arm. Otherwise, adjust inward and determine the nut afterwards.


14. Tail seal station adjusts the up and down orientation of the tail seal tool holder according to the requirements of the pipe, and the gap between the tail seal tools is about 0. 2mm.


15. Turn on the power and air supply, start the active operating system and enter the active operation of the fully active filling and sealing machine.


16. Forbid non-protective operators to adjust various setting parameters arbitrarily. If the settings are not correct, the equipment may not work properly and may be damaged in serious cases. If adjustment is needed in the process of use, it must be done when the machine is suspended.


17. It is forbidden to adjust the unit while it is in operation.


18. Press the stop button and then turn off the power switch and air supply switch.


19. Feeding equipment and filling and sealing machine equipment of thorough cleaning. 


20. record the operation condition and daily protection of the equipment.

url: http://m.wwwu88.cn/en/news/505.html

深圳市昌浩慧豐實業(yè)有限公司



Shenzhen Changhao Huifeng Industrial Co.

9F, Zhengke Times, No.17, Industrial Road 1, Da Wang Shan, Shajing Street, Baoan District, Shenzhen

Copyright@2023粵ICP備15020808號